One of the challenges of explaining project management to people who are unfamiliar with the approach, is that descriptions are often either so high-level as to be meaningless, or so detailed that they are overwhelming. Over the years, I have come to use a model as a framework for introducing and discussing project management tools and techniques. It can be used as the basis for a five-minute explanation of what is involved in project management, but also as an outline for more detailed discussions. (The actual model can be found on the Key Consulting website under free templates and info.)

A brief description of each step follows:

Assemble Team

The project planning team will be assembled, including appropriate representation from customers/clients, and sometimes subcontractors and vendors. Initial roles and responsibilities will be defined.

Deliverables: Initial project setup documentation.

Define Project Objective

With the project team in place, the overall project purpose will be verified and detailed project objectives developed. A phase-exit review will be conducted to ensure that the project is ready to move into the next phase, which is planning.

Deliverables: project charter, phase-exit review checklist.

Define Project Scope

An appropriately detailed Work Breakdown Structure (WBS) will be developed to ensure the project scope is properly agreed to and understood by all stakeholders. This also allows the complete project to be split into appropriate sub-projects and/or phases.

Deliverables: Project work breakdown structure.

Construct an Initial Plan

Once tasks of an appropriate level have been identified in the WBS, they will be organised by the project team into logical network diagrams, with estimated durations. This allows the project manager to predict when activities will be complete, assess the feasibility of target dates, and identify the critical path for the project.

Deliverables: Initial work plan.

Add Resources, Costs, Risks, etc.

Certain project resources may be defined as critical resources. In particular, the project manager may suspect that key project staff may be faced with too much work. If so, estimated resource usage information can be added to the project plan to allow resource forecasting. Cost is obviously also critically important, and expenditures can be added to the plan to create estimated cash-flow requirements. Risk management can also be utilised on projects to provide a framework to better manage events that occur beyond the control of the project team.

Deliverables: Resource availability and commitment profiles, risk identification and control strategies, cash-flow forecasts.

Obtain Stakeholder Buy-in

To ensure the project is implemented as smoothly as possible, with the support of the involved parties, it will be necessary to review the initial plans with all the major project stakeholders and to solicit buy-in from each one. A phase-exit review will be conducted to ensure that the project is ready to move into the next phase, which is control.

Deliverables: Approved final plan, phase-exit review checklist.

Publish the Plan

Once the plans are agreed to, they must be effectively communicated to all stakeholders. This can be done in hard copy or via electronic media, depending on the resources available. On most projects, a communications plan will be developed, and distribution of the plans will follow the guidelines laid out in the communications plan.

Deliverables: Plan published to all stakeholders.

Collect Progress Information

On a regular basis, the project manager will collect progress information that has been reported by the project team. This will allow the compilation of progress reports, such as:

  • Activities completed within the past two weeks.
  • Activities forecast for the next two weeks with a focus on activities on the critical path.
  • Funds expended vs. fund expenditure forecast.
  • Prioritised issues report.

Metrics can also be developed to measure project progress in other ways, such as earned value, or activity float statistics. If the project manager reviews the progress data and concludes that the project is complete, a phase-exit review will be completed to confirm that all the objectives have been met before moving into the final closure phase.

Deliverables: Set of progress reports, set of exception reports, metrics report, (phase-exit review checklist).

Analyse Current Status

By analysing the progress information received, the project manager will be able to augment the above reports with information about which areas of the project are of concern and where problems are likely to occur in the future. This allows managers to focus on the important/critical areas of the project.

Deliverables: Project evaluation report(s).

Adjust the Plan, and Manage Project Change

Based on the analysis, and with the support of the project team, the project manager will make plan adjustments to help reduce risks, accommodate scope changes, or to compensate for activities that have not occurred on schedule. Once this has happened, the plan will re-published and the cycle repeated until the project is complete.

Deliverables: Change request forms, updated plan.

Close Project

When the objectives of the project have been achieved, the project manager will close down the project. This will involve some financial closure tasks, as well as archiving of the project materials. A lessons-learned document will be developed to benefit future projects, and if possible a project team celebration will be held.

Deliverables: Final project report including lessons learned.

The Simplified Project Management Process的更多相关文章

  1. Project Management Process

    Project Management ProcessDescription .............................................................. ...

  2. Introduction to Project Management(II)

    Introduction The purpose of this paper is to gain an understanding of project management and to give ...

  3. Introduction to Project Management(I)

    Project management in the modern sense began in the early 1950s, although it has its roots further b ...

  4. 【转】bug management process

    What is Bug? A bug is the consequence/outcome of a coding fault What is Defect? A defect is a variat ...

  5. 简介 - PMP(Project Management Professional)

    PMP(Project Management Professional) 官网(英文报名):https://www.pmi.org/ 中文注册:http://exam.chinapmp.cn/ Boo ...

  6. 10 Rules of Highly Successful Project Management

    I commited the information below to report PDU of PMI. ^_^. In this paper, the author introduces his ...

  7. Software Engineering: 2. Project management

    resources:"Software Engineering" Ian Sommerville For most projects, important goals are: D ...

  8. Software Project Management hw1

    I just want to say something about my java project that I did last year. Our task is to finish a lin ...

  9. Linux Process Management && Process Scheduling Principle

    目录 . 引言 . 进程优先级 . 进程的生命周 . 进程表示 . 进程管理相关的系统调用 . 进程调度 . 完全公平调度类 . 实时调度类 . 调度器增强 . 小结 1. 引言 在多处理器系统中,可 ...

随机推荐

  1. 【BZOJ】1901: Zju2112 Dynamic Rankings(区间第k小+树状数组套主席树)

    http://www.lydsy.com/JudgeOnline/problem.php?id=1901 首先还是吐槽时间,我在zoj交无限tle啊!!!!!!!!我一直以为是程序错了啊啊啊啊啊啊. ...

  2. 【BZOJ】1059: [ZJOI2007]矩阵游戏(二分图匹配)

    http://www.lydsy.com/JudgeOnline/problem.php?id=1059 本题可以看出,无论怎样变化,在同一行和同一列的数永远都不会分手---还是吐槽,,我第一眼yy了 ...

  3. html ul 里 能放其他标签吗,比如h3、p?

    按标准的话,ul 里面应该只能放li,不过看见同事有的放了h3.p这些,这样到底可不可以?   <ul>里面只能放<li>.但是<li>里面可以放<h*> ...

  4. spark-submit [options]

    执行时需要传入的参数说明如下: Usage: spark-submit [options] <app jar | python file> [app options] 参数名称 含义 -- ...

  5. git subtree用法(转)

    git subtree用法 一.使用场景 例如,在项目Game中有一个子目录AI.Game和AI分别是一个独立的git项目,可以分开维护.为了避免直接复制粘贴代码,我们希望Game中的AI子目录与AI ...

  6. apache日志文件太大的问题

    apache日志文件太大的问题 处理Apache日志的两种方法 rotatelogs 是 Apache 2.2 中自带的管道日志程序 rotatelogs [ -l ] logfile [ rotat ...

  7. QT学习之-HelloWorld

    实现HelloWorld有2种方法. 第一种在mainwindow.ui直接添加Label且写上“HelloWorld”. 第二种是代码直接实现 #include "mainwindow.h ...

  8. 郎科U208(主控 PS2251-50 HYNIX H27UCG8T2MYR)量产还原

    6年前的一个U盘 记得还是参加某会议送的,当时做了量产 多做了一个光盘区,现在用不着了  想还原成普通U盘 忘了方法. 可见笔记的重要性 Chipgenius看了主控 PS2251-50 芯片是海力士 ...

  9. mysql的udf应用

    一.mysql的Mysql-udf-http参见文章http://blog.s135.com/mysql-udf-http/ 注:centos安装后如果无法提交数据,请关闭selinux二.mysql ...

  10. PHP学习(二)----数组

    数组: 首先说一下对PHP中的理解,建立一个好的理解模型还是很关键的: 1.PHP中的数组实际上可以理解为键值对,key=>value;而对于key的取值,可以是string/integer;v ...