Using Change Management and Change Control Within a Project
In any project, change is inevitable whether it comes from within the project or from external sources, therefore it makes sense to have an agreed process in order to identify, assess and control any potential and approved changes to what was originally agreed for the project.
What is needed is a systematic and common approach. Once the project plan and other key associated documents have been approved, these become the project "baselines" and can only be changed after approval by the appropriate authority, normally the Project Board. Change control is not there to prevent changes, but to ensure that every change is agreed by the relevant authority before implementation.
An important and vital element, is the projects use of configuration management (CM). Configuration management may be provided as a continuous organisational service or be provided by a Project Support Office (PSO). Everything that the project produces is subject to configuration management, this includes management documentation as well as specialist products and deliverables. It is important therefore to integrate the use of change control procedures with the configuration management system used by the project.
The system that is set-up to manage change should also include the management of the general issues. An Issue Register should be set up early in the project to capture and assist in the management of change and issues. A configuration management strategy document must be created as part of planning and this defines the way in which changes and issues are to be managed and handled throughout the project.
The difference between an issue and a risk is that the issue has already happened, whereas a risk is something that may or may not happen at some point in the future.
Whenever an issue is raised, it may be managed informally, usually by the project manager, however if it is to be managed formally then the project manager would enter it into the issue register before proceeding any further. The PRINCE2 methodology states that an Issue Report is created in tandem and contains supplementary information regarding that particular issue.
Changes come in two flavours:
Request For Change (RFC). This comes from the customer or user and is a request to change one of the project baselines in some way. If there are any extra costs involved in implementing the RFC, then the customer would normally pay for it. Since all RFC's are a change to what had been originally agreed, it is normally the Project Board alone will have the authority to agree such changes.
Off Specification. These are normally raised from the supply side of the project, and details some aspect that should be provided by the project, but currently is not, or is forecast not to be provided. This might include products or deliverables that are missing, or a product not meeting its specification or quality criteria.
At the beginning of a project it needs to be decided how changes and issues are to be prioritised, and it is usual that a ratings system might include terms such as, Must Have, Should Have, Could Have, or Won't Have For Now. Such definitions need to be agreed.
Another aspect that needs to be decided is whether or not the Project Board or senior management wanted to be involved in reviewing all project changes. If many changes are predicted then it may make sense for the Project Board to appoint a change authority who would make decisions on such changes on behalf of the Project Board. In such cases, the "rules of engagement" needs to be determined.
For example, the change authority would only deal with low cost changes. Another aspect is setting up a change budget for the change authority to use to fund any approved changes and their implementation. Such additional budgets should be captured within the project plan before sign-off.
Onwards to the change control procedure itself...
Step 1. Whenever a change or issue is raised, it should be categorised and entered in the issue/change register.
Step 2. An impact analysis should now be carried out and will normally involve relevant specialist team members.
The impact analysis should consider the change or issue impact (which may be positive or negative) on a variety of projects aspects such as:
- Time
- Cost
- Quality
- Scope
- Business Case
- Benefits
- Risk
The change or issue should be prioritised, first, by the originator, and second, after impact analysis. It is important when carrying out the above impact analysis, that representatives from the project business area, the users of the end products, and those who are supplying resources to the project, are fully involved so that a balanced decision can be reached.
Step 3. Having understood the full impact of the change or issue, the next step is to consider alternative options and proposing the best actions to take in order to resolve the issue or implement the change. A balanced view is needed and consideration should be given all these options on the projects duration, cost, quality, scope, benefit, and risk performance targets. The advantages gained should be balanced against the impact of implementing the issue or change.
Step 4. A decision is now needed whether or not to implement the change. For a RFC, this would normally need escalating to the Project Board for their decision, whereas an Off-Specification may be decided by the project manager if they have sufficient authority.
If the project is using Management By Exception where tolerance boundaries have been set, then should any proposed implementation deviate beyond these tolerances, the Project Board must be involved in the decision whether to implement or not.
During implementation, the project manager should ensure that its status is reported to the Project Board up to the point when the issue or change has been fully implemented.
Using Change Management and Change Control Within a Project的更多相关文章
- Training - Problem and Change Management
Problem Management Problem management seeks to identify the underlying causes of incidents in an IT ...
- input输入框的的input事件和change事件以及change和blur事件的区别
input输入框的 oninput事件 ,在用户输入的时候触发,只要元素值发生变化就会触发 input输入框的 onchange事件 ,要在输入框失去焦点的时候触发事件,当鼠标在其他地方点击一下才会触 ...
- (IDEA) VCS-->Import Into Version Control没有Share Project(Subversion)这个选项。
在VCS-->Import Into Version Control,会发现只有Import Into Subversion选项,并没有Share Project(Subversion)这个选项 ...
- SAP Change Request Management (ChaRM)基础教程
本文介绍了SAP Solution Manager中的变更请求管理工具(Change Request Management,以下简称ChaRM ). 最近打算写个上线前请求号检查工具,为此需要了解相关 ...
- [ScreenOS] How to change the certificate that is used for SSL (HTTPS) WebUI Management
SUMMARY: This article provides information on how to change the certificate that is used for SSL (HT ...
- [AX]AX2012 R2 采购订单的“Request change”
在采购订单List或者Detail窗口的操作面板上有一个叫做“Request change”的按钮,如果这个按钮是激活的,采购订单不能直接编辑,而必须先使用这个按钮请求修改后,采购订单才能进入编辑状态 ...
- 【Gerrit】Gerrit cmd query (gerrit命令行查询change信息)
本文仅展现个人使用情况和理解,英文原址:https://review.openstack.org/Documentation/cmd-query.html 基本使用格式: ssh -p <por ...
- $().change事件
change([[data],fn]) 当元素的value值发生改变时发生change事件 适用于: 文本域 text textarea和select元素 text textarea 元素失去焦点时发 ...
- easyui给select控件绑定change事件
一般的做法是使用jQuery来绑定,例如: $("#id").change(function(){ alert("change事件绑定"); }); 当给sel ...
随机推荐
- TYVJ P1086 Elevator Label:dp
背景 广东汕头聿怀初中 Train#2 Problem4 描述 现有N种箱子,每种箱子高度H_i,数量C_i.现选取若干箱子堆成一列,且第i种箱子不能放在高度超过A_i的地方.试求最大叠放高度. 输入 ...
- RSA密钥的生成与配置
openssl下载地址http://dldx.csdn.net/fd.php?i=20313208579480&s=ac2e809e168f7d5b8bf1515d3d6b1aa4,或者官方下 ...
- 理解with(nolock)(转载)
本文导读:要 提升SQL的查询效能,一般来说大家会以建立索引(index)为第一考虑.其实除了index的建立之外,当我们在下SQL Command时,在语法中加一段WITH (NOLOCK)可以改善 ...
- shell 循环
for循环: 批量删除.gz结尾的文件: 循环打包文件并备份到一个目录下面: find ./ -maxdepth 1 -name "*.gz" find ./ -maxdepth ...
- 分布式架构高可用架构篇_04_Keepalived+Nginx实现高可用Web负载均衡
参考: 龙果学院http://www.roncoo.com/share.html?hamc=hLPG8QsaaWVOl2Z76wpJHp3JBbZZF%2Bywm5vEfPp9LbLkAjAnB%2B ...
- EasyUI datagrid 在ie8和360兼容模式兼容性问题
问题:easyui中的datagrid在ie8和360兼容模式下显示不出来. 答案:不是easyui的问题.是引入的jquery版本问题.jquery-1.5.1抛异常,这个版本是mvc3自带的jqu ...
- Win2008R2 zip格式mysql 安装与配置
一.百度mysql5.6 ZIP 64位免安装版 下载好后 解压到D盘下 二.可以考虑修改my.ini里面的配置 character-set-server=utf8 这句是编码格式设定 ...
- CentOS 6 RPM安裝python 2.7
先说第一种方法,通过rpmbuild编译XXX.src.rpm包([1].[2]): 安装依赖:sudo yum install -y make autoconf bzip2-devel db4-de ...
- ubuntu lnmp
apt-get update apt-get upgrade apt-get install libxml2 libxml2-dev apt-get install make apt-get inst ...
- ArcGIS Server发布服务,报错00032
错误00032 独立表数据源无法访问 00032: 修复已断开的数据连接,具体做法是将每个独立表的数据源都设置为正确的位置. 或者,如果不需要该表,将其从文档中移除. 建议在ArcMap中重新加载数据 ...