recourse: "Software Engineering", Ian Sommerville


Keywords for this chapter:

  • planning
  • scheduling
  • cost estimation

Project planning takes place at three stages in a project life cycle:

  • At the proposal stage (When you are bidding for a contract to develop or provide a software system).

    • Do you have the resources to complete the work?
    • work out the price that you should quote to a customer.
  • During the project startup phase When you have to plan:
    • who will work on the project
    • how the project will be broken down into increments
    • how resources will be allocated across your company
    • etc
  • Periodically throughout the project

Planning at the proposal stage is inevitably speculative [ɪ'nevɪtəblɪ] ['spekjʊlətɪv] , as you do not usually have a complete set of requirements for the software to be developed. Rather, you have to respond to a call for proposals based on a high-level description of the software functionality that is required.

There are three main parameters that you should use when computing the costs of a software development project:

  • effort costs ( the costs of paying software engineers and managers)
  • hardware and software costs, including maintenance
  • travel and training costs

The plan should define project monitoring mechnisms. You must keep track of the progress of the project and compare actual and planned progress and costs.

Agood manager should be able to form a clear picture of what is going on through informal discussions with project staff.

1. Software pricing

When calculating a price, you should take the following iterms into account:

  • Market opportunity
  • Cost estimate uncertainty
  • Contractual terms
  • Requirements volatility
  • Financial health

1.1 market opportunity

A development organization may quote a low price because it wishes to move into a new segment of the software market. Accepting a low profit on one project may give the organization the opportunity to make a greater profit later. The experience gained may also help it develop new products.

1.2 Cost estimate uncertainty

If an organization is unsure of its cost estimate, it may increase its price by a contingency over and above its normal profit.

1.3 Contractual terms

A customer may be willing to allow the developer to retain ownership of the source code and reuse it in other prohects. The price charged may then be less than if the software source code is handed over to the customer.

1.4 Requirements volatility

If the requirements are likely to change, an organization may lower its price to win a contract. After the contract is awarded, high prices can be charged for changes to hte requirements.

1.5 Financial health

Developers in financial difficulty may lower their price to gain a contract. It is better to make a smaller than normal profit or break even than to go out of business. Cash flow is more important than profit in difficult economic times.

2. Plan-driven development

Plan-driven or plan-based development is an approach to software engineering where the development process is planned in detail.

2.1 Project plans

In a plan-driven development project, a project plan normally include the following sections:

  1. Introduction: This briefly describes the objectives of the project and sets out the constraints (e.g., budget, time, etc.) that affect the management of the project.
  2. Poject organization: This describes the way in which the development team its organized, the people involved, and their roles in the team.
  3. Risk analysis: This describes possible project risks, the likelihood of these risks arising, and the risk reduction strategies that are proposed.
  4. Hardware and software resource requirements
  5. Work breakdown: milestones and deliverables associated with each activity.
  6. Project schedul
  7. Monitoring and reporting mechanisms : This defines the management reports that should be produced, when these should be produced, and the project monitoring mechanisms to be used.

2.2 The planning process

The figure below is a UML activity diagram that shows a typical workflow for a project planning process.

contraints: delivery date, staff available, overall budget, available tools, and so on.

3. Project scheduling

Project scheduleing is the process of deciding:

  • how the work will be organized as separate tasks
  • when and how these tasks will be executed
  • calandar time
  • who will work on the tasks
  • resources needed

3.1 Schedule representation

Project schedules may simply be represented in a table or spreadsheet showing the tasks,effort, expected duration, and task dependencies.

There are two types of representation that are commonly used:

  • Bar charts: calendar-based, show who is responsible for each activity, the expected elapsed time, and when the activity is scheduled to begin and end. (Gantt charts)
  • Activity networks: network diagrams, show the dependencies between the different activities making up a project.

Project activities are the basic planning element. Each activity has:

  • a duration in clendar days or months
  • an effort estimate
  • a deadline
  • a defined endpoint. This represents the tangible result of completing the activity. This coud be a document, the holding of a review meeting, the successful execution of all tests, etc.

The table below shows tasks, estimated effort, duration, and task interdependencies.

It can be seen from the table that T3 is dependent on task T1. Task T1 must, therefore, be completed before T starts.

The bar chart below takes the information in table above and presents the project schedule in a graphical format.

Project managers have to allocate resources to tasks as well.

The table below shows when staff are working on the project.

4. Agile planning

Agile methods of software development are iterative approaches where the software is developedand delivered to customers inincrements.

(important but skip here)

Software Engineering: 3. Project planning的更多相关文章

  1. SENG201 (Software Engineering I) Project

    SENG201 (Software Engineering I) ProjectSpace ExplorerFor project admin queries:For project help, hi ...

  2. Software Engineering: 2. Project management

    resources:"Software Engineering" Ian Sommerville For most projects, important goals are: D ...

  3.  Go is more about software engineering than programming language research.

    https://talks.golang.org/2012/splash.article Go at Google: Language Design in the Service of Softwar ...

  4. 第二篇——The communication during software engineering.

    I've learned a lot in my software engineering class about how a program comes out.That's also a esse ...

  5. 2.2 CMMI2级——项目计划(Project Planning)

    大家都明白这样的一个道理:做事情要有计划,有一个不成熟的计划总比没有计划要好,软件开发这么复杂的活动,更加需要计划.那么应该怎样做好一个计划呢? 如果对项目的范围.规模.性质.任务.工作量.费用等都不 ...

  6. Software Engineering: 1. Introduction

    Resource: Ian, Sommerville, Software Engineering 1. Professional software development 1.1 Software e ...

  7. 个人阅读作业2—《No Silver Bullet: Essence and Accidents of Software Engineering》读后感

    在进行了一次结对编程.一次团队编程和一次个人编程项目后,读了<No Silver Bullet: Essence and Accidents of Software Engineering> ...

  8. Software Engineering at Google

    Google的Fergus Henderson在Software Engineering at Google中介绍了Google的软件工程实践. 软件开发 源码仓库 单一源代码仓库,除了核心配置和安全 ...

  9. Limeng:Individual Project: Word frequency program -BUAA Advanced Software Engineering

    11061190-李孟 Implement a console application to tally the frequency of words under a directory (2 mod ...

随机推荐

  1. Immutable笔记

    Immutable笔记 转换成js数据 获取或则改变嵌套式imutable数据类型  

  2. Java连接SqlServer2008数据库(转)

    Java连接SqlServer2008数据库 首先下载JDBC:下载地址:http://www.microsoft.com/zh-cn/download/details.aspx?id=21599 下 ...

  3. asp.net页面生命周期请求管道19个事件

    HttpContext: ecb→ HttpWorkerRequest→HttpContext HttpApplicationFactory.获取了HttpApplication实例之后. (1)Be ...

  4. 30分钟学会如何使用Shiro

    本篇内容大多总结自张开涛的<跟我学Shiro>原文地址:http://jinnianshilongnian.iteye.com/blog/2018936 我并没有全部看完,只是选择了一部分 ...

  5. CSS3 笔记三(Shadow/Text/Web Fonts)

    CSS3 Shadow Effects text-shadow box-shadow 1> text-shadow The text-shadow property adds shadow to ...

  6. JAVA NIO——Buffer和FileChannel

    Java NIO和IO的主要区别 IO NIO 面向流 面向缓冲 阻塞IO 非阻塞IO 无 选择器 示例: import java.io.FileInputStream; import java.io ...

  7. Android Paint的属性

    在Paint中有很多的属性可以设置,比如可以设置阴影,颜色过滤等等,这些会产生不同的奇妙效果,今天就对各种属性探索一下. 方法一: 1 //设置绘制的颜色,a代表透明度,r,g,b代表颜色值. 2 s ...

  8. proxifier 3.29 key

    Proxifier 3.29 serial key :-   [Use only One ]  (Standard Edition Keys) 5EZ8G-C3WL5-B56YG-SCXM9-6QZA ...

  9. HTMl链接- target/ name

    下面解释一下链接标签的另外两个属性:target和name HTML 链接 - target 属性 使用 Target 属性,你可以定义被链接的文档在何处显示. 下面的这行会在新窗口打开文档: < ...

  10. Java SE 基础:标识(zhì)符

    Java SE 基础:标识(zhì)符 一.标识符定义 标识符,就是给类.接口.方法.变量等起名字时的字符序列 二.组成规则与注意事项 1.组成规则 英文大小写字母 数组 $ 和 _ 2.注意事项 不 ...