recourse: "Software Engineering", Ian Sommerville


Keywords for this chapter:

  • planning
  • scheduling
  • cost estimation

Project planning takes place at three stages in a project life cycle:

  • At the proposal stage (When you are bidding for a contract to develop or provide a software system).

    • Do you have the resources to complete the work?
    • work out the price that you should quote to a customer.
  • During the project startup phase When you have to plan:
    • who will work on the project
    • how the project will be broken down into increments
    • how resources will be allocated across your company
    • etc
  • Periodically throughout the project

Planning at the proposal stage is inevitably speculative [ɪ'nevɪtəblɪ] ['spekjʊlətɪv] , as you do not usually have a complete set of requirements for the software to be developed. Rather, you have to respond to a call for proposals based on a high-level description of the software functionality that is required.

There are three main parameters that you should use when computing the costs of a software development project:

  • effort costs ( the costs of paying software engineers and managers)
  • hardware and software costs, including maintenance
  • travel and training costs

The plan should define project monitoring mechnisms. You must keep track of the progress of the project and compare actual and planned progress and costs.

Agood manager should be able to form a clear picture of what is going on through informal discussions with project staff.

1. Software pricing

When calculating a price, you should take the following iterms into account:

  • Market opportunity
  • Cost estimate uncertainty
  • Contractual terms
  • Requirements volatility
  • Financial health

1.1 market opportunity

A development organization may quote a low price because it wishes to move into a new segment of the software market. Accepting a low profit on one project may give the organization the opportunity to make a greater profit later. The experience gained may also help it develop new products.

1.2 Cost estimate uncertainty

If an organization is unsure of its cost estimate, it may increase its price by a contingency over and above its normal profit.

1.3 Contractual terms

A customer may be willing to allow the developer to retain ownership of the source code and reuse it in other prohects. The price charged may then be less than if the software source code is handed over to the customer.

1.4 Requirements volatility

If the requirements are likely to change, an organization may lower its price to win a contract. After the contract is awarded, high prices can be charged for changes to hte requirements.

1.5 Financial health

Developers in financial difficulty may lower their price to gain a contract. It is better to make a smaller than normal profit or break even than to go out of business. Cash flow is more important than profit in difficult economic times.

2. Plan-driven development

Plan-driven or plan-based development is an approach to software engineering where the development process is planned in detail.

2.1 Project plans

In a plan-driven development project, a project plan normally include the following sections:

  1. Introduction: This briefly describes the objectives of the project and sets out the constraints (e.g., budget, time, etc.) that affect the management of the project.
  2. Poject organization: This describes the way in which the development team its organized, the people involved, and their roles in the team.
  3. Risk analysis: This describes possible project risks, the likelihood of these risks arising, and the risk reduction strategies that are proposed.
  4. Hardware and software resource requirements
  5. Work breakdown: milestones and deliverables associated with each activity.
  6. Project schedul
  7. Monitoring and reporting mechanisms : This defines the management reports that should be produced, when these should be produced, and the project monitoring mechanisms to be used.

2.2 The planning process

The figure below is a UML activity diagram that shows a typical workflow for a project planning process.

contraints: delivery date, staff available, overall budget, available tools, and so on.

3. Project scheduling

Project scheduleing is the process of deciding:

  • how the work will be organized as separate tasks
  • when and how these tasks will be executed
  • calandar time
  • who will work on the tasks
  • resources needed

3.1 Schedule representation

Project schedules may simply be represented in a table or spreadsheet showing the tasks,effort, expected duration, and task dependencies.

There are two types of representation that are commonly used:

  • Bar charts: calendar-based, show who is responsible for each activity, the expected elapsed time, and when the activity is scheduled to begin and end. (Gantt charts)
  • Activity networks: network diagrams, show the dependencies between the different activities making up a project.

Project activities are the basic planning element. Each activity has:

  • a duration in clendar days or months
  • an effort estimate
  • a deadline
  • a defined endpoint. This represents the tangible result of completing the activity. This coud be a document, the holding of a review meeting, the successful execution of all tests, etc.

The table below shows tasks, estimated effort, duration, and task interdependencies.

It can be seen from the table that T3 is dependent on task T1. Task T1 must, therefore, be completed before T starts.

The bar chart below takes the information in table above and presents the project schedule in a graphical format.

Project managers have to allocate resources to tasks as well.

The table below shows when staff are working on the project.

4. Agile planning

Agile methods of software development are iterative approaches where the software is developedand delivered to customers inincrements.

(important but skip here)

Software Engineering: 3. Project planning的更多相关文章

  1. SENG201 (Software Engineering I) Project

    SENG201 (Software Engineering I) ProjectSpace ExplorerFor project admin queries:For project help, hi ...

  2. Software Engineering: 2. Project management

    resources:"Software Engineering" Ian Sommerville For most projects, important goals are: D ...

  3.  Go is more about software engineering than programming language research.

    https://talks.golang.org/2012/splash.article Go at Google: Language Design in the Service of Softwar ...

  4. 第二篇——The communication during software engineering.

    I've learned a lot in my software engineering class about how a program comes out.That's also a esse ...

  5. 2.2 CMMI2级——项目计划(Project Planning)

    大家都明白这样的一个道理:做事情要有计划,有一个不成熟的计划总比没有计划要好,软件开发这么复杂的活动,更加需要计划.那么应该怎样做好一个计划呢? 如果对项目的范围.规模.性质.任务.工作量.费用等都不 ...

  6. Software Engineering: 1. Introduction

    Resource: Ian, Sommerville, Software Engineering 1. Professional software development 1.1 Software e ...

  7. 个人阅读作业2—《No Silver Bullet: Essence and Accidents of Software Engineering》读后感

    在进行了一次结对编程.一次团队编程和一次个人编程项目后,读了<No Silver Bullet: Essence and Accidents of Software Engineering> ...

  8. Software Engineering at Google

    Google的Fergus Henderson在Software Engineering at Google中介绍了Google的软件工程实践. 软件开发 源码仓库 单一源代码仓库,除了核心配置和安全 ...

  9. Limeng:Individual Project: Word frequency program -BUAA Advanced Software Engineering

    11061190-李孟 Implement a console application to tally the frequency of words under a directory (2 mod ...

随机推荐

  1. BufferedReader与BufferedWriter读写中文乱码问题

    正常读写英文时用""""没问题 FileReader fre = new FileReader("E:\\TEST\\readText.txt&quo ...

  2. h5视频上传之前端视频压缩研究

    今天领导接到一个h5上传手机视频的需求,主要是要看用户在这个视频中有没有完成某个任务,比如投篮进了几个球. 但是由于手机拍摄的视频文件大小有点大,直接上传的话,用户流量顶不住,而且特别耗时,在这样的情 ...

  3. Andrion错误解决:cannot be resolved or is not a field

    cannot be resolved or is not a field   解决这个问题:   选择project菜单中的clean,选择你的项目,先clean一下, 再去看看Activity中有没 ...

  4. [综合]visio2013安装提示找不到Office.zh_cn\officeMUI.mis officemui.xml

    在visio2013安装提示找不到Office.zh_cn\officeMUI.mis officemui.xml 等等,各种提示,可是打开安装程序所在的ISO,里面可是“赶集网”——啥都有啊.上网查 ...

  5. Windows Azure Virtual Machine 之用程序控制Azure VM

    我们在很多时候可能会需要用程序来控制VM的创建,删除工作. 而在这些工作之中,用程序创建一个VM将会是一个非常复杂的过程,因为他涉及到很多步骤. 具体步骤如下 1 创建一个Hosted cloud s ...

  6. qt qml scrollbar 移动APP风格的滚动轴

    依附于Flickable组件的滚动轴    自动放置在恰当位置    拖动时显示,不动时消失Lisence: MIT 请保留此声明Author: surfsky.cnblogs.com 2014-12 ...

  7. PhpStorm创建Drupal模块项目开发教程(3)

    rush是 Drupal的脚本界面,PhpStorm的命令行工具支持Drush 5.8和更高版本. 接下来就Drush配置和基本操作进行设置,首先点击打开Settings | Command Line ...

  8. 鸟哥的linux私房菜学习记录之软件安装RPM,SRPM,YUM

  9. [Java Web]Error parsing HTTP request header Note: further occurrences of HTTP header parsing errors

    手机客户端向服务器提交Http请求时,Tomcat抛出错误: 十二月 31, 2014 2:32:45 下午 org.apache.coyote.http11.AbstractHttp11Proces ...

  10. InnoDB事务隔离级别

    转载于:http://blog.csdn.net/wudongxu/article/details/8623610 SQL标准定义了4类隔离级别,包括了一些具体规则,用来限定事务内外的哪些改变是可见的 ...