Software Engineering: 3. Project planning
recourse: "Software Engineering", Ian Sommerville
Keywords for this chapter:
- planning
- scheduling
- cost estimation
Project planning takes place at three stages in a project life cycle:
- At the proposal stage (When you are bidding for a contract to develop or provide a software system).
- Do you have the resources to complete the work?
- work out the price that you should quote to a customer.
- During the project startup phase When you have to plan:
- who will work on the project
- how the project will be broken down into increments
- how resources will be allocated across your company
- etc
- Periodically throughout the project
Planning at the proposal stage is inevitably speculative [ɪ'nevɪtəblɪ] ['spekjʊlətɪv] , as you do not usually have a complete set of requirements for the software to be developed. Rather, you have to respond to a call for proposals based on a high-level description of the software functionality that is required.
There are three main parameters that you should use when computing the costs of a software development project:
- effort costs ( the costs of paying software engineers and managers)
- hardware and software costs, including maintenance
- travel and training costs
The plan should define project monitoring mechnisms. You must keep track of the progress of the project and compare actual and planned progress and costs.
Agood manager should be able to form a clear picture of what is going on through informal discussions with project staff.
1. Software pricing
When calculating a price, you should take the following iterms into account:
- Market opportunity
- Cost estimate uncertainty
- Contractual terms
- Requirements volatility
- Financial health
1.1 market opportunity
A development organization may quote a low price because it wishes to move into a new segment of the software market. Accepting a low profit on one project may give the organization the opportunity to make a greater profit later. The experience gained may also help it develop new products.
1.2 Cost estimate uncertainty
If an organization is unsure of its cost estimate, it may increase its price by a contingency over and above its normal profit.
1.3 Contractual terms
A customer may be willing to allow the developer to retain ownership of the source code and reuse it in other prohects. The price charged may then be less than if the software source code is handed over to the customer.
1.4 Requirements volatility
If the requirements are likely to change, an organization may lower its price to win a contract. After the contract is awarded, high prices can be charged for changes to hte requirements.
1.5 Financial health
Developers in financial difficulty may lower their price to gain a contract. It is better to make a smaller than normal profit or break even than to go out of business. Cash flow is more important than profit in difficult economic times.
2. Plan-driven development
Plan-driven or plan-based development is an approach to software engineering where the development process is planned in detail.
2.1 Project plans
In a plan-driven development project, a project plan normally include the following sections:
- Introduction: This briefly describes the objectives of the project and sets out the constraints (e.g., budget, time, etc.) that affect the management of the project.
- Poject organization: This describes the way in which the development team its organized, the people involved, and their roles in the team.
- Risk analysis: This describes possible project risks, the likelihood of these risks arising, and the risk reduction strategies that are proposed.
- Hardware and software resource requirements
- Work breakdown: milestones and deliverables associated with each activity.
- Project schedul
- Monitoring and reporting mechanisms : This defines the management reports that should be produced, when these should be produced, and the project monitoring mechanisms to be used.
2.2 The planning process
The figure below is a UML activity diagram that shows a typical workflow for a project planning process.

contraints: delivery date, staff available, overall budget, available tools, and so on.
3. Project scheduling
Project scheduleing is the process of deciding:
- how the work will be organized as separate tasks
- when and how these tasks will be executed
- calandar time
- who will work on the tasks
- resources needed
3.1 Schedule representation
Project schedules may simply be represented in a table or spreadsheet showing the tasks,effort, expected duration, and task dependencies.
There are two types of representation that are commonly used:
- Bar charts: calendar-based, show who is responsible for each activity, the expected elapsed time, and when the activity is scheduled to begin and end. (Gantt charts)
- Activity networks: network diagrams, show the dependencies between the different activities making up a project.
Project activities are the basic planning element. Each activity has:
- a duration in clendar days or months
- an effort estimate
- a deadline
- a defined endpoint. This represents the tangible result of completing the activity. This coud be a document, the holding of a review meeting, the successful execution of all tests, etc.
The table below shows tasks, estimated effort, duration, and task interdependencies.
It can be seen from the table that T3 is dependent on task T1. Task T1 must, therefore, be completed before T starts.

The bar chart below takes the information in table above and presents the project schedule in a graphical format.

Project managers have to allocate resources to tasks as well.
The table below shows when staff are working on the project.

4. Agile planning
Agile methods of software development are iterative approaches where the software is developedand delivered to customers inincrements.
(important but skip here)
Software Engineering: 3. Project planning的更多相关文章
- SENG201 (Software Engineering I) Project
SENG201 (Software Engineering I) ProjectSpace ExplorerFor project admin queries:For project help, hi ...
- Software Engineering: 2. Project management
resources:"Software Engineering" Ian Sommerville For most projects, important goals are: D ...
- Go is more about software engineering than programming language research.
https://talks.golang.org/2012/splash.article Go at Google: Language Design in the Service of Softwar ...
- 第二篇——The communication during software engineering.
I've learned a lot in my software engineering class about how a program comes out.That's also a esse ...
- 2.2 CMMI2级——项目计划(Project Planning)
大家都明白这样的一个道理:做事情要有计划,有一个不成熟的计划总比没有计划要好,软件开发这么复杂的活动,更加需要计划.那么应该怎样做好一个计划呢? 如果对项目的范围.规模.性质.任务.工作量.费用等都不 ...
- Software Engineering: 1. Introduction
Resource: Ian, Sommerville, Software Engineering 1. Professional software development 1.1 Software e ...
- 个人阅读作业2—《No Silver Bullet: Essence and Accidents of Software Engineering》读后感
在进行了一次结对编程.一次团队编程和一次个人编程项目后,读了<No Silver Bullet: Essence and Accidents of Software Engineering> ...
- Software Engineering at Google
Google的Fergus Henderson在Software Engineering at Google中介绍了Google的软件工程实践. 软件开发 源码仓库 单一源代码仓库,除了核心配置和安全 ...
- Limeng:Individual Project: Word frequency program -BUAA Advanced Software Engineering
11061190-李孟 Implement a console application to tally the frequency of words under a directory (2 mod ...
随机推荐
- XiangBai——【AAAI2017】TextBoxes_A Fast Text Detector with a Single Deep Neural Network
XiangBai--[AAAI2017]TextBoxes:A Fast Text Detector with a Single Deep Neural Network 目录 作者和相关链接 方法概括 ...
- ajaxfileupload 传参数
引用:http://www.cnblogs.com/lyeo/archive/2012/05/11/2496261.html 直接上代码: var data = { name: 'my name', ...
- AppCan开发者资料分享(定期更新)
开发者培训 上海20150925开发者培训资料:链接:http://pan.baidu.com/s/1mgCLzz6 密码:mqgi 版权声明:本文为博主原创文章,未经博主允许不得转载.
- 物理引擎-Physx的源代码去哪里找
前几天无意中看到了Physx开源了,就连自己的领导也高兴了一下,让本道士去下载源代码琢磨一下,顺便做几个例子跑起来.结果没成想这个nvidia的github上的源代码被移除了,而且csdn,pudn上 ...
- 【数学】Jersey Politics
Jersey Politics Time Limit: 1000MS Memory ...
- java第六次作业(老师讲过后)
import java.util.*; public class Draw { private ArrayList list; public Draw() { list= new ArrayList( ...
- 字符串操作 replace
"hello".charAt(0); // "h" "hello, world".replace("hello", &q ...
- Linux_用户级_常用命令(3):mkdir
Linux常用命令之mkdir 开篇语:懒是人类进步的源动力 本文原创,专为光荣之路公众号所有,欢迎转发,但转发请务必写出处! Linux常用命令第3集包含命令:mkdir (附赠tree命令,日期时 ...
- LR中线程和进程的区别
LoadRunner中的进程与线程 1.进程与线程的区别: 进程和线程的区别是什么?进程和线程都是由操作系统所体会的程序运行的基本单元,系统利用该基本单元实现系统对应用的并发性.进程和线程的区别 ...
- C#数组
数组是一种数据结构,它包含若干相同类型的变量.数组是使用类型声明的: type[] arrayName; 下面的示例创建一维.多维和交错数组: class TestArraysClass { stat ...