The Simplified Project Management Process
One of the challenges of explaining project management to people who are unfamiliar with the approach, is that descriptions are often either so high-level as to be meaningless, or so detailed that they are overwhelming. Over the years, I have come to use a model as a framework for introducing and discussing project management tools and techniques. It can be used as the basis for a five-minute explanation of what is involved in project management, but also as an outline for more detailed discussions. (The actual model can be found on the Key Consulting website under free templates and info.)
A brief description of each step follows:
Assemble Team
The project planning team will be assembled, including appropriate representation from customers/clients, and sometimes subcontractors and vendors. Initial roles and responsibilities will be defined.
Deliverables: Initial project setup documentation.
Define Project Objective
With the project team in place, the overall project purpose will be verified and detailed project objectives developed. A phase-exit review will be conducted to ensure that the project is ready to move into the next phase, which is planning.
Deliverables: project charter, phase-exit review checklist.
Define Project Scope
An appropriately detailed Work Breakdown Structure (WBS) will be developed to ensure the project scope is properly agreed to and understood by all stakeholders. This also allows the complete project to be split into appropriate sub-projects and/or phases.
Deliverables: Project work breakdown structure.
Construct an Initial Plan
Once tasks of an appropriate level have been identified in the WBS, they will be organised by the project team into logical network diagrams, with estimated durations. This allows the project manager to predict when activities will be complete, assess the feasibility of target dates, and identify the critical path for the project.
Deliverables: Initial work plan.
Add Resources, Costs, Risks, etc.
Certain project resources may be defined as critical resources. In particular, the project manager may suspect that key project staff may be faced with too much work. If so, estimated resource usage information can be added to the project plan to allow resource forecasting. Cost is obviously also critically important, and expenditures can be added to the plan to create estimated cash-flow requirements. Risk management can also be utilised on projects to provide a framework to better manage events that occur beyond the control of the project team.
Deliverables: Resource availability and commitment profiles, risk identification and control strategies, cash-flow forecasts.
Obtain Stakeholder Buy-in
To ensure the project is implemented as smoothly as possible, with the support of the involved parties, it will be necessary to review the initial plans with all the major project stakeholders and to solicit buy-in from each one. A phase-exit review will be conducted to ensure that the project is ready to move into the next phase, which is control.
Deliverables: Approved final plan, phase-exit review checklist.
Publish the Plan
Once the plans are agreed to, they must be effectively communicated to all stakeholders. This can be done in hard copy or via electronic media, depending on the resources available. On most projects, a communications plan will be developed, and distribution of the plans will follow the guidelines laid out in the communications plan.
Deliverables: Plan published to all stakeholders.
Collect Progress Information
On a regular basis, the project manager will collect progress information that has been reported by the project team. This will allow the compilation of progress reports, such as:
- Activities completed within the past two weeks.
- Activities forecast for the next two weeks with a focus on activities on the critical path.
- Funds expended vs. fund expenditure forecast.
- Prioritised issues report.
Metrics can also be developed to measure project progress in other ways, such as earned value, or activity float statistics. If the project manager reviews the progress data and concludes that the project is complete, a phase-exit review will be completed to confirm that all the objectives have been met before moving into the final closure phase.
Deliverables: Set of progress reports, set of exception reports, metrics report, (phase-exit review checklist).
Analyse Current Status
By analysing the progress information received, the project manager will be able to augment the above reports with information about which areas of the project are of concern and where problems are likely to occur in the future. This allows managers to focus on the important/critical areas of the project.
Deliverables: Project evaluation report(s).
Adjust the Plan, and Manage Project Change
Based on the analysis, and with the support of the project team, the project manager will make plan adjustments to help reduce risks, accommodate scope changes, or to compensate for activities that have not occurred on schedule. Once this has happened, the plan will re-published and the cycle repeated until the project is complete.
Deliverables: Change request forms, updated plan.
Close Project
When the objectives of the project have been achieved, the project manager will close down the project. This will involve some financial closure tasks, as well as archiving of the project materials. A lessons-learned document will be developed to benefit future projects, and if possible a project team celebration will be held.
Deliverables: Final project report including lessons learned.
The Simplified Project Management Process的更多相关文章
- Project Management Process
Project Management ProcessDescription .............................................................. ...
- Introduction to Project Management(II)
Introduction The purpose of this paper is to gain an understanding of project management and to give ...
- Introduction to Project Management(I)
Project management in the modern sense began in the early 1950s, although it has its roots further b ...
- 【转】bug management process
What is Bug? A bug is the consequence/outcome of a coding fault What is Defect? A defect is a variat ...
- 简介 - PMP(Project Management Professional)
PMP(Project Management Professional) 官网(英文报名):https://www.pmi.org/ 中文注册:http://exam.chinapmp.cn/ Boo ...
- 10 Rules of Highly Successful Project Management
I commited the information below to report PDU of PMI. ^_^. In this paper, the author introduces his ...
- Software Engineering: 2. Project management
resources:"Software Engineering" Ian Sommerville For most projects, important goals are: D ...
- Software Project Management hw1
I just want to say something about my java project that I did last year. Our task is to finish a lin ...
- Linux Process Management && Process Scheduling Principle
目录 . 引言 . 进程优先级 . 进程的生命周 . 进程表示 . 进程管理相关的系统调用 . 进程调度 . 完全公平调度类 . 实时调度类 . 调度器增强 . 小结 1. 引言 在多处理器系统中,可 ...
随机推荐
- 大白话strom——问题收集(持续更新ing)
本文导读: 1.基于storm的应用 2.storm的单点故障解决 3.strom与算法的结合学习4.杂记——常见问题的解答5.http://www.blogchong.com/catalog.asp ...
- JavaScript中toStirng()与Object.prototype.toString.call()方法浅谈
toStirng()与Object.prototype.toString.call()方法浅谈 一.toString()是一个怎样的方法?它是能将某一个值转化为字符串的方法.然而它是如何将一个值从一种 ...
- [Unity2D]实现背景的移动
在游戏中通常会实现的效果是玩家主角移动的时候,背景也可以跟着移动,要实现这种效果其实就是获取主角的位置,然后再改变摄像机的位置就可以了,这就需要通过脚本来实现.这个脚本添加到摄像机的GameObjec ...
- git 用Gitk /usr/bin/which: no wish
/usr/bin/which: no wish 安装yum -y install tcl 和yum -y install tk 显示所有的分支 $gitk --all 显示所有的分支 $gitk -- ...
- Android由一个activity 间隔5秒自动跳转到另外一个activity
Android由一个activity 间隔5秒自动跳转到另外一个activity 2013年10月10日18:03:42 //一.写一个定时器 5秒后开启 final Intent lo ...
- FLTK 1.3.3 VS 2010 Configuration 配置
Download FLTK 1.3.3 Download VS2010 I assume you've already installed VS2010 correctly. Compile the ...
- Java主要有那几种文件类型,各自作用
java提供了两类数据类型:基本类型,引用类型. 1.基本类型包括:boolean ,byte,char,int,short,float,long,double,值得注意的是:在原始数据类型中,除了b ...
- python 操作mysql
安装模块: #pip install .... MySQLdb(2.x) pymysql(3.x) import MySQLdb as sql con = sql.connect( host = &q ...
- PHP文件漏桐可以通过对服务器进行设置和配置来达到防范目的
对脚本执行漏洞的防范 黑客利用脚本执行漏洞进行攻击的手段是多种多样的,而且是灵活多变的,对此,必须要采用多种防范方法综合的手段,才能有效防止黑客对脚本执行漏洞进行攻击.这里常用的方法方法有以下四种.一 ...
- 如何在URL筛选管理器中过滤不需要的URL
互联网可以说是一把名副其实的双刃剑.一方面其可以提高工作效率.给企业提供充分的资源;另一方面如果管理不严,也会带来很多的隐患.如员工在上班时间玩游戏.炒股等等.为此现在很多企业希望对员工的网络行为进行 ...