The Simplified Project Management Process
One of the challenges of explaining project management to people who are unfamiliar with the approach, is that descriptions are often either so high-level as to be meaningless, or so detailed that they are overwhelming. Over the years, I have come to use a model as a framework for introducing and discussing project management tools and techniques. It can be used as the basis for a five-minute explanation of what is involved in project management, but also as an outline for more detailed discussions. (The actual model can be found on the Key Consulting website under free templates and info.)
A brief description of each step follows:
Assemble Team
The project planning team will be assembled, including appropriate representation from customers/clients, and sometimes subcontractors and vendors. Initial roles and responsibilities will be defined.
Deliverables: Initial project setup documentation.
Define Project Objective
With the project team in place, the overall project purpose will be verified and detailed project objectives developed. A phase-exit review will be conducted to ensure that the project is ready to move into the next phase, which is planning.
Deliverables: project charter, phase-exit review checklist.
Define Project Scope
An appropriately detailed Work Breakdown Structure (WBS) will be developed to ensure the project scope is properly agreed to and understood by all stakeholders. This also allows the complete project to be split into appropriate sub-projects and/or phases.
Deliverables: Project work breakdown structure.
Construct an Initial Plan
Once tasks of an appropriate level have been identified in the WBS, they will be organised by the project team into logical network diagrams, with estimated durations. This allows the project manager to predict when activities will be complete, assess the feasibility of target dates, and identify the critical path for the project.
Deliverables: Initial work plan.
Add Resources, Costs, Risks, etc.
Certain project resources may be defined as critical resources. In particular, the project manager may suspect that key project staff may be faced with too much work. If so, estimated resource usage information can be added to the project plan to allow resource forecasting. Cost is obviously also critically important, and expenditures can be added to the plan to create estimated cash-flow requirements. Risk management can also be utilised on projects to provide a framework to better manage events that occur beyond the control of the project team.
Deliverables: Resource availability and commitment profiles, risk identification and control strategies, cash-flow forecasts.
Obtain Stakeholder Buy-in
To ensure the project is implemented as smoothly as possible, with the support of the involved parties, it will be necessary to review the initial plans with all the major project stakeholders and to solicit buy-in from each one. A phase-exit review will be conducted to ensure that the project is ready to move into the next phase, which is control.
Deliverables: Approved final plan, phase-exit review checklist.
Publish the Plan
Once the plans are agreed to, they must be effectively communicated to all stakeholders. This can be done in hard copy or via electronic media, depending on the resources available. On most projects, a communications plan will be developed, and distribution of the plans will follow the guidelines laid out in the communications plan.
Deliverables: Plan published to all stakeholders.
Collect Progress Information
On a regular basis, the project manager will collect progress information that has been reported by the project team. This will allow the compilation of progress reports, such as:
- Activities completed within the past two weeks.
- Activities forecast for the next two weeks with a focus on activities on the critical path.
- Funds expended vs. fund expenditure forecast.
- Prioritised issues report.
Metrics can also be developed to measure project progress in other ways, such as earned value, or activity float statistics. If the project manager reviews the progress data and concludes that the project is complete, a phase-exit review will be completed to confirm that all the objectives have been met before moving into the final closure phase.
Deliverables: Set of progress reports, set of exception reports, metrics report, (phase-exit review checklist).
Analyse Current Status
By analysing the progress information received, the project manager will be able to augment the above reports with information about which areas of the project are of concern and where problems are likely to occur in the future. This allows managers to focus on the important/critical areas of the project.
Deliverables: Project evaluation report(s).
Adjust the Plan, and Manage Project Change
Based on the analysis, and with the support of the project team, the project manager will make plan adjustments to help reduce risks, accommodate scope changes, or to compensate for activities that have not occurred on schedule. Once this has happened, the plan will re-published and the cycle repeated until the project is complete.
Deliverables: Change request forms, updated plan.
Close Project
When the objectives of the project have been achieved, the project manager will close down the project. This will involve some financial closure tasks, as well as archiving of the project materials. A lessons-learned document will be developed to benefit future projects, and if possible a project team celebration will be held.
Deliverables: Final project report including lessons learned.
The Simplified Project Management Process的更多相关文章
- Project Management Process
Project Management ProcessDescription .............................................................. ...
- Introduction to Project Management(II)
Introduction The purpose of this paper is to gain an understanding of project management and to give ...
- Introduction to Project Management(I)
Project management in the modern sense began in the early 1950s, although it has its roots further b ...
- 【转】bug management process
What is Bug? A bug is the consequence/outcome of a coding fault What is Defect? A defect is a variat ...
- 简介 - PMP(Project Management Professional)
PMP(Project Management Professional) 官网(英文报名):https://www.pmi.org/ 中文注册:http://exam.chinapmp.cn/ Boo ...
- 10 Rules of Highly Successful Project Management
I commited the information below to report PDU of PMI. ^_^. In this paper, the author introduces his ...
- Software Engineering: 2. Project management
resources:"Software Engineering" Ian Sommerville For most projects, important goals are: D ...
- Software Project Management hw1
I just want to say something about my java project that I did last year. Our task is to finish a lin ...
- Linux Process Management && Process Scheduling Principle
目录 . 引言 . 进程优先级 . 进程的生命周 . 进程表示 . 进程管理相关的系统调用 . 进程调度 . 完全公平调度类 . 实时调度类 . 调度器增强 . 小结 1. 引言 在多处理器系统中,可 ...
随机推荐
- state配置语言实战
修改配置文件:(base用来放初始化环境.prod用来放生产配置环境) [root@super65 ~]# vim /etc/salt/master [root@super65 ~]# mkdir - ...
- jdk+myeclipse配置安装相关步骤
1.JDK的安装JDK 版本:7u25 安装路径:c:\java(注意:装不装公共jre都可,自己可以选择安装到哪里)环境变量配置:(1)JAVA_HOME:C:\Java(就是你安装jdk的目录 ...
- 【iBoard电子学堂】【iCore双核心板】资料光盘A盘更新,版本号为A6
_____________________________________ 深入交流QQ群: A: 204255896(1000人超级群,可加入) B: 165201798(500人超级群,满员) C ...
- MySQL助理配置
基本配置 你需要经常察看以下3个配置项.不然,可能很快就会出问题. innodb_buffer_pool_size:这是你安装完InnoDB后第一个应该设置的选项.缓冲池是数据和索引缓存的地方:这个值 ...
- axure rp extension的下载
使用chrome无法直接打开axure制作的prd文档,需要下载相关插件.平时用的shadowsocksFQ软件,登录chrome的网上应用商店,确发现无法正常下载, 于是通过其他途径下载了改插件,拖 ...
- Antialiasing with Transparency
Antialiasing with Transparency This sample demonstrates the GeForce 7 Series per-primitive super-sam ...
- 每天学点GDB 11
为了跟踪glibc库中函数的执行,需要带有debug symbol的glibc, 如果是debian或者是基于debian的发行版本如ubuntu和linuxmint之类的,很简单执行如下指令安装即可 ...
- Javascript 笔记与总结(1-6)Javascript 面向对象
在 JavaScript 中,有对象,没有类(但有构造函数). 在 JavaScript 中,对象不依赖于类而存在,可以直接生成. {key:value, key:value} 这种格式的对象,成为 ...
- 简单实现Redis缓存中的排序功能
1.在实现缓存排序功能之前,必须先明白这一功能的合理性.不妨思考一下,既然可以在数据库中排序,为什么还要把排序功能放在缓存中实现呢?这里简单总结了两个原因:首先,排序会增加数据库的负载,难以支撑高并发 ...
- 省略nslog打印
//#if #endif宏定义的意思就是如果定义了DEBUG,那么就使用NSLog输出:否则这段代码直接忽略.有人会疑问这个DEBUG和_DEBUG来自哪里,这个其实不用担心,这个来自于Xcode的默 ...